How Long Does a Building Permit Take in Sacramento?
By Liberty Drafting Studios
Sacramento permit timelines explained — from plan submittal to approval. Learn what causes delays and how to get your permit faster in 2026.
One of the most common questions we hear from Sacramento homeowners is: "How long will my permit take?"
The answer varies — but after coordinating hundreds of permits across Sacramento County, the City of Sacramento, Roseville, Elk Grove, and surrounding jurisdictions, we know exactly what to expect and how to avoid the delays that slow most projects down.
Typical Sacramento Permit Timelines in 2026
Here's a realistic breakdown of permit timelines for common residential projects:
| Project Type | Over-the-Counter | Plan Check (Standard) | Plan Check (Expedited) |
|---|---|---|---|
| Simple remodel (no structural) | Same day – 1 week | 4–8 weeks | 2–3 weeks |
| ADU / Garage Conversion | Not eligible | 8–16 weeks | 4–8 weeks |
| Home Addition | Not eligible | 10–20 weeks | 5–10 weeks |
| New Custom Home | Not eligible | 12–24 weeks | 6–12 weeks |
Important: These are plan check timelines only — the time from submitting your plans to receiving approval (or correction comments). Construction time is separate.
The Sacramento Permit Process: Step by Step
Step 1: Prepare Permit-Ready Plans (2–6 weeks)
Before you can submit anything, you need complete architectural drawings. This is where most projects either succeed or fail — incomplete or incorrect plans are the #1 cause of permit delays.
A proper permit submittal for Sacramento includes:
- Site plan with setbacks and lot coverage calculations
- Floor plans (existing and proposed)
- Elevations (all four sides)
- Structural details and calculations
- Title 24 energy compliance documentation
- Grading and drainage plan (for new construction)
At Liberty Drafting Studios, we prepare permit-ready plans that are complete on the first submittal — which is the single biggest factor in getting your permit faster.
Step 2: Submit to the Building Department
Sacramento has multiple jurisdictions, each with their own process:
- City of Sacramento: Online submittal via eTRAKiT portal
- Sacramento County (unincorporated): Online or in-person
- Roseville, Elk Grove, Folsom, etc.: Each city has its own portal
We handle submittal coordination for our clients — navigating the right portal, paying fees, and tracking status.
Step 3: Plan Check (The Waiting Game)
This is where most of the time is spent. A plan checker reviews your drawings for code compliance. In Sacramento, plan check times have improved since 2023 but still run:
- Standard plan check: 6–16 weeks depending on project complexity and current backlog
- Expedited plan check: 3–8 weeks (costs 50–100% more in fees)
Step 4: Correction Responses (If Needed)
Most projects receive at least one round of correction comments — questions or required changes from the plan checker. How quickly you respond determines how quickly you move forward.
This is where having an experienced designer pays off. We respond to corrections within 48–72 hours and know exactly what the plan checkers are looking for.
Step 5: Permit Issuance
Once your plans are approved, you pay the remaining permit fees and receive your permit. You're now cleared to start construction.
What Causes Permit Delays?
1. Incomplete plans — Missing details, wrong scale, or missing required documents send your project back to square one.
2. Correction response delays — Some homeowners or designers take weeks to respond to correction comments. We respond in days.
3. Jurisdiction backlog — Some cities are simply busier than others. Sacramento County unincorporated areas tend to be faster than the City of Sacramento.
4. Structural engineering requirements — Projects requiring stamped structural calculations add time. We coordinate with licensed engineers to keep this moving.
5. HOA approval — If your property is in an HOA, you need their approval before or alongside the city permit. Don't forget this step.
How to Get Your Permit Faster
1. Start with complete, correct plans. This is the single most impactful thing you can do. Incomplete plans = multiple rounds of corrections = months of delay.
2. Use expedited plan check. For time-sensitive projects, paying the expedited fee is almost always worth it.
3. Respond to corrections immediately. When the plan checker sends comments, respond within 24–48 hours.
4. Work with someone who knows the local process. Each Sacramento-area jurisdiction has quirks. We know them.
5. Don't start construction before permit issuance. Unpermitted work creates massive problems — stop-work orders, fines, and required demolition.
Sacramento vs. Other Bay Area Cities
Sacramento is generally faster and less expensive for permits than the Bay Area. San Francisco and San Jose can take 12–24+ months for ADU permits. Sacramento typically runs 3–6 months for a complete ADU permit cycle — much more manageable.
Ready to Start?
The permit process starts with great plans. At Liberty Drafting Studios, we've guided hundreds of Sacramento homeowners through the permit process — from first sketch to approved permit.
Call David at 916-694-9949 for a free project review, or start with our online calculator to estimate your design costs.
Explore Topics
Written by
David Ardelian, Liberty Drafting Studios
Founder of Liberty Drafting Studios, serving Greater Sacramento with permit-ready architectural plans for ADUs, garage conversions, custom homes, and remodels.